Question 21 / 40:  A hydroelectric dam on the Ochlockonee River was built in 1929. The elevation change in water level from above the dam to below the dam is about 10 m. The hydroelectric plant on the dam is capable of producing as much as 12 MW of electrical power. Which of the following is the best estimate of the flow rate of water through the dam at peak generation rate?
A  100,000 m3/s
B  10,000 m3/s
C  1000 m3/s
D  100 m3/s
E  10 m3/s
<< First < Previous Flashcard Next > Last >>
Explanation:

q = 12 x 106 W / (9.8 m2/s x 10 m x 1000 kg/m3)

Quiz Home Page
https://www.jobilize.com/fluid-mechanics-mcq-quiz-by-stephanie-redfern-tuan-dinh

Fluid Mechanics ME201

Author:

Access: Public Instant Grading

Attribution:  Stephanie Redfern and Tuan Dinh. Fluid Mechanics. The Saylor Academy 2014, http://www.saylor.org/courses/me201/
Ask
George Turner
Start Quiz
Sarah Warren
Start Test
Yacoub Jayoghli
Start Quiz
Copy and paste the following HTML code into your website or blog.
<iframe src="https://www.jobilize.com/embed/fluid-mechanics-mcq-quiz-by-stephanie-redfern-tuan-dinh" width="600" height="600" frameborder="0" marginwidth="0" marginheight="0" scrolling="yes" style="border:1px solid #CCC; border-width:1px 1px 0; margin-bottom:5px" allowfullscreen webkitallowfullscreen mozallowfullscreen> </iframe>